REMIT POWER PLANTS
MARKET PARTECIPATION ID
12XAET-HANDEL-3
AFFECTED REGIONAL AREA
SWISSGRID
LAST UPDATE
16.10.2024 01:03 UTC
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
16.10.2024 05:00 UTC
EVENT END
16.10.2024 08:00 UTC
UNIT
Verzasca
UNAVAILABILITY
38.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
16.10.2024 09:15 UTC
EVENT END
16.10.2024 10:45 UTC
UNIT
Verzasca
UNAVAILABILITY
38.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
16.10.2024 11:00 UTC
EVENT END
16.10.2024 12:30 UTC
UNIT
Verzasca
UNAVAILABILITY
38.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
16.10.2024 13:45 UTC
EVENT END
16.10.2024 16:00 UTC
UNIT
Verzasca
UNAVAILABILITY
38.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
17.10.2024 05:00 UTC
EVENT END
17.10.2024 08:00 UTC
UNIT
Verzasca
UNAVAILABILITY
38.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
17.10.2024 09:15 UTC
EVENT END
17.10.2024 10:45 UTC
UNIT
Verzasca
UNAVAILABILITY
38.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
21.10.2024 05:00 UTC
EVENT END
22.10.2024 10:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
22.10.2024 10:30 UTC
EVENT END
22.10.2024 14:30 UTC
UNIT
Leventina
UNAVAILABILITY
72.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
22.10.2024 14:30 UTC
EVENT END
23.10.2024 10:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
23.10.2024 10:30 UTC
EVENT END
23.10.2024 14:30 UTC
UNIT
Leventina
UNAVAILABILITY
72.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
23.10.2024 14:30 UTC
EVENT END
24.10.2024 10:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
24.10.2024 10:30 UTC
EVENT END
24.10.2024 14:30 UTC
UNIT
Leventina
UNAVAILABILITY
57.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
24.10.2024 14:30 UTC
EVENT END
29.10.2024 11:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
29.10.2024 11:30 UTC
EVENT END
29.10.2024 15:30 UTC
UNIT
Leventina
UNAVAILABILITY
74.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
29.10.2024 15:30 UTC
EVENT END
30.10.2024 15:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
06.11.2024 11:30 UTC
EVENT END
06.11.2024 15:30 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
07.11.2024 11:30 UTC
EVENT END
07.11.2024 15:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
11.11.2024 06:00 UTC
EVENT END
13.11.2024 11:30 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
13.11.2024 11:30 UTC
EVENT END
13.11.2024 15:30 UTC
UNIT
Leventina
UNAVAILABILITY
30.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
13.11.2024 15:30 UTC
EVENT END
15.11.2024 15:00 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
19.11.2024 11:30 UTC
EVENT END
19.11.2024 15:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
21.11.2024 11:30 UTC
EVENT END
21.11.2024 15:30 UTC
UNIT
Leventina
UNAVAILABILITY
57.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
24.11.2024 23:00 UTC
EVENT END
26.11.2024 11:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
26.11.2024 11:30 UTC
EVENT END
26.11.2024 15:30 UTC
UNIT
Leventina
UNAVAILABILITY
74.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
26.11.2024 15:30 UTC
EVENT END
04.12.2024 11:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
04.12.2024 11:30 UTC
EVENT END
04.12.2024 15:30 UTC
UNIT
Leventina
UNAVAILABILITY
72.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
04.12.2024 15:30 UTC
EVENT END
05.12.2024 11:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
05.12.2024 11:30 UTC
EVENT END
05.12.2024 15:30 UTC
UNIT
Leventina
UNAVAILABILITY
98.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
05.12.2024 15:30 UTC
EVENT END
11.12.2024 11:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
11.12.2024 11:30 UTC
EVENT END
11.12.2024 15:30 UTC
UNIT
Leventina
UNAVAILABILITY
56.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
11.12.2024 15:30 UTC
EVENT END
12.12.2024 11:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
12.12.2024 11:30 UTC
EVENT END
12.12.2024 15:30 UTC
UNIT
Leventina
UNAVAILABILITY
72.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
12.12.2024 15:30 UTC
EVENT END
13.12.2024 16:00 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
17.12.2024 11:30 UTC
EVENT END
17.12.2024 15:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
18.12.2024 11:30 UTC
EVENT END
18.12.2024 15:30 UTC
UNIT
Leventina
UNAVAILABILITY
32.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
19.12.2024 11:30 UTC
EVENT END
19.12.2024 15:30 UTC
UNIT
Leventina
UNAVAILABILITY
57.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
13.01.2025 06:00 UTC
EVENT END
25.04.2025 16:00 UTC
UNIT
Verzasca
UNAVAILABILITY
38.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
24.03.2025 20:30 UTC
EVENT END
27.03.2025 23:30 UTC
UNIT
Leventina
UNAVAILABILITY
154.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
26.10.2025 06:00 UTC
EVENT END
01.11.2025 18:00 UTC
UNIT
Leventina
UNAVAILABILITY
14.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
01.01.2026 23:00 UTC
EVENT END
29.03.2026 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
12.01.2026 06:00 UTC
EVENT END
24.04.2026 16:00 UTC
UNIT
Verzasca
UNAVAILABILITY
38.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
30.06.2026 22:00 UTC
EVENT END
01.01.2027 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
01.01.2027 23:00 UTC
EVENT END
30.01.2027 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
86.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
18.01.2027 06:00 UTC
EVENT END
18.01.2027 16:00 UTC
UNIT
Verzasca
UNAVAILABILITY
38.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
18.01.2027 16:00 UTC
EVENT END
29.01.2027 16:00 UTC
UNIT
Verzasca
UNAVAILABILITY
114.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
29.01.2027 16:00 UTC
EVENT END
23.04.2027 16:00 UTC
UNIT
Verzasca
UNAVAILABILITY
38.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
30.01.2027 23:00 UTC
EVENT END
16.03.2027 05:00 UTC
UNIT
Leventina
UNAVAILABILITY
72.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
16.03.2027 05:00 UTC
EVENT END
16.03.2027 16:00 UTC
UNIT
Leventina
UNAVAILABILITY
79.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
16.03.2027 16:00 UTC
EVENT END
17.03.2027 05:00 UTC
UNIT
Leventina
UNAVAILABILITY
72.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
17.03.2027 05:00 UTC
EVENT END
17.03.2027 16:00 UTC
UNIT
Leventina
UNAVAILABILITY
79.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
17.03.2027 16:00 UTC
EVENT END
23.03.2027 05:00 UTC
UNIT
Leventina
UNAVAILABILITY
72.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
23.03.2027 05:00 UTC
EVENT END
23.03.2027 16:00 UTC
UNIT
Leventina
UNAVAILABILITY
121.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
23.03.2027 16:00 UTC
EVENT END
25.03.2027 05:00 UTC
UNIT
Leventina
UNAVAILABILITY
72.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
25.03.2027 05:00 UTC
EVENT END
25.03.2027 16:00 UTC
UNIT
Leventina
UNAVAILABILITY
121.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
25.03.2027 16:00 UTC
EVENT END
28.03.2027 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
72.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
28.03.2027 22:00 UTC
EVENT END
30.04.2027 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
14.07.2027 22:00 UTC
EVENT END
31.12.2027 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
31.12.2027 23:00 UTC
EVENT END
01.01.2028 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
30.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
01.01.2028 23:00 UTC
EVENT END
02.01.2028 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
79.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
02.01.2028 23:00 UTC
EVENT END
31.01.2028 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
184.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
10.01.2028 06:00 UTC
EVENT END
17.03.2028 17:00 UTC
UNIT
Verzasca
UNAVAILABILITY
38.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
31.01.2028 23:00 UTC
EVENT END
31.03.2028 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
86.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
31.03.2028 22:00 UTC
EVENT END
01.04.2028 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
30.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
01.04.2028 22:00 UTC
EVENT END
16.04.2028 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
14.07.2028 22:00 UTC
EVENT END
02.01.2029 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
25.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
02.01.2029 23:00 UTC
EVENT END
29.03.2029 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
172.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
29.03.2029 22:00 UTC
EVENT END
16.04.2029 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
25.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
01.01.2030 23:00 UTC
EVENT END
03.01.2030 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
147.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
03.01.2030 23:00 UTC
EVENT END
18.01.2030 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
154.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
18.01.2030 23:00 UTC
EVENT END
31.01.2030 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
147.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
23.03.2032 05:00 UTC
EVENT END
23.03.2032 16:00 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
24.03.2032 05:00 UTC
EVENT END
24.03.2032 16:00 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
25.03.2032 05:00 UTC
EVENT END
25.03.2032 16:00 UTC
UNIT
Leventina
UNAVAILABILITY
25.00 MW