Azienda Elettrica Ticinese
REMIT POWER PLANTS


MARKET PARTECIPATION ID
12XAET-HANDEL-3

AFFECTED REGIONAL AREA
SWISSGRID

LAST UPDATE
18.09.2021 01:58 UTC

PRODUCTION PLANNED UNAVAILABILITY
EVENT START
21.09.2021 05:00 UTC
EVENT END
21.09.2021 09:00 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
22.09.2021 05:00 UTC
EVENT END
22.09.2021 05:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
22.09.2021 05:30 UTC
EVENT END
22.09.2021 09:00 UTC
UNIT
Leventina
UNAVAILABILITY
57.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
23.09.2021 05:00 UTC
EVENT END
23.09.2021 09:00 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
27.09.2021 05:00 UTC
EVENT END
01.10.2021 15:00 UTC
UNIT
Leventina
UNAVAILABILITY
14.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
04.10.2021 05:00 UTC
EVENT END
08.10.2021 14:00 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
11.10.2021 05:00 UTC
EVENT END
14.10.2021 05:00 UTC
UNIT
Leventina
UNAVAILABILITY
25.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
14.10.2021 05:00 UTC
EVENT END
14.10.2021 09:00 UTC
UNIT
Leventina
UNAVAILABILITY
74.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
14.10.2021 09:00 UTC
EVENT END
15.10.2021 14:30 UTC
UNIT
Leventina
UNAVAILABILITY
25.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
18.10.2021 05:00 UTC
EVENT END
19.10.2021 05:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
19.10.2021 05:30 UTC
EVENT END
19.10.2021 09:30 UTC
UNIT
Leventina
UNAVAILABILITY
56.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
19.10.2021 09:30 UTC
EVENT END
20.10.2021 05:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
20.10.2021 05:30 UTC
EVENT END
20.10.2021 09:30 UTC
UNIT
Leventina
UNAVAILABILITY
57.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
20.10.2021 09:30 UTC
EVENT END
21.10.2021 05:00 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
21.10.2021 05:00 UTC
EVENT END
21.10.2021 09:00 UTC
UNIT
Leventina
UNAVAILABILITY
72.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
21.10.2021 09:00 UTC
EVENT END
22.10.2021 14:00 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
25.10.2021 05:00 UTC
EVENT END
29.10.2021 14:30 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
08.11.2021 06:00 UTC
EVENT END
12.11.2021 15:00 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
16.11.2021 06:00 UTC
EVENT END
16.11.2021 10:00 UTC
UNIT
Leventina
UNAVAILABILITY
25.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
17.11.2021 06:00 UTC
EVENT END
17.11.2021 10:00 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
18.11.2021 06:00 UTC
EVENT END
18.11.2021 10:00 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
23.11.2021 06:00 UTC
EVENT END
23.11.2021 10:00 UTC
UNIT
Leventina
UNAVAILABILITY
56.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
24.11.2021 06:30 UTC
EVENT END
24.11.2021 10:30 UTC
UNIT
Leventina
UNAVAILABILITY
15.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
30.11.2021 06:00 UTC
EVENT END
30.11.2021 10:00 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
09.12.2021 06:00 UTC
EVENT END
09.12.2021 10:00 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
10.12.2021 06:00 UTC
EVENT END
10.12.2021 10:00 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
14.12.2021 06:00 UTC
EVENT END
14.12.2021 10:00 UTC
UNIT
Leventina
UNAVAILABILITY
25.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
15.12.2021 06:00 UTC
EVENT END
15.12.2021 10:00 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
21.12.2021 06:00 UTC
EVENT END
21.12.2021 06:30 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
21.12.2021 06:30 UTC
EVENT END
21.12.2021 10:00 UTC
UNIT
Leventina
UNAVAILABILITY
30.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
22.12.2021 06:00 UTC
EVENT END
22.12.2021 06:30 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
22.12.2021 06:30 UTC
EVENT END
22.12.2021 10:00 UTC
UNIT
Leventina
UNAVAILABILITY
57.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
02.01.2022 23:00 UTC
EVENT END
03.01.2022 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
03.01.2022 06:00 UTC
EVENT END
15.04.2022 15:00 UTC
UNIT
Verzasca
UNAVAILABILITY
114.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
03.01.2022 23:00 UTC
EVENT END
28.03.2022 19:30 UTC
UNIT
Leventina
UNAVAILABILITY
72.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
28.03.2022 19:30 UTC
EVENT END
31.03.2022 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
170.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
31.03.2022 22:00 UTC
EVENT END
31.03.2022 22:30 UTC
UNIT
Leventina
UNAVAILABILITY
147.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
09.10.2022 22:00 UTC
EVENT END
27.10.2022 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
14.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
27.10.2022 22:00 UTC
EVENT END
09.12.2022 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
93.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
09.12.2022 23:00 UTC
EVENT END
01.01.2023 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
79.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
01.01.2023 23:00 UTC
EVENT END
02.01.2023 06:00 UTC
UNIT
Leventina
UNAVAILABILITY
128.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
02.01.2023 06:00 UTC
EVENT END
03.01.2023 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
135.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
03.01.2023 23:00 UTC
EVENT END
27.01.2023 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
142.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
27.01.2023 23:00 UTC
EVENT END
03.03.2023 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
135.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
01.03.2023 06:00 UTC
EVENT END
30.04.2023 21:00 UTC
UNIT
Verzasca
UNAVAILABILITY
38.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
03.03.2023 23:00 UTC
EVENT END
10.03.2023 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
79.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
10.03.2023 23:00 UTC
EVENT END
29.03.2023 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
56.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
26.11.2023 23:00 UTC
EVENT END
01.01.2024 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
01.01.2024 23:00 UTC
EVENT END
05.03.2024 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
105.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
01.03.2024 06:00 UTC
EVENT END
30.04.2024 16:00 UTC
UNIT
Verzasca
UNAVAILABILITY
38.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
05.03.2024 23:00 UTC
EVENT END
29.03.2024 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
56.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
10.04.2024 22:00 UTC
EVENT END
16.04.2024 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
14.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
01.01.2025 23:00 UTC
EVENT END
28.03.2025 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
49.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
01.03.2025 06:00 UTC
EVENT END
30.04.2025 16:00 UTC
UNIT
Verzasca
UNAVAILABILITY
38.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
14.07.2025 22:00 UTC
EVENT END
01.01.2026 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
25.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
01.01.2026 23:00 UTC
EVENT END
30.01.2026 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
88.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
30.01.2026 23:00 UTC
EVENT END
31.03.2026 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
74.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
31.03.2026 22:00 UTC
EVENT END
16.04.2026 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
25.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
14.07.2026 22:00 UTC
EVENT END
16.04.2027 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
14.07.2027 22:00 UTC
EVENT END
31.12.2027 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
31.12.2027 23:00 UTC
EVENT END
02.01.2028 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
30.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
02.01.2028 23:00 UTC
EVENT END
31.01.2028 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
184.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
31.01.2028 23:00 UTC
EVENT END
31.03.2028 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
37.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
31.03.2028 22:00 UTC
EVENT END
01.04.2028 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
30.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
01.04.2028 22:00 UTC
EVENT END
16.04.2028 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
23.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
02.01.2029 23:00 UTC
EVENT END
29.03.2029 22:00 UTC
UNIT
Leventina
UNAVAILABILITY
147.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
01.01.2030 23:00 UTC
EVENT END
03.01.2030 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
147.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
03.01.2030 23:00 UTC
EVENT END
18.01.2030 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
154.00 MW
PRODUCTION PLANNED UNAVAILABILITY
EVENT START
18.01.2030 23:00 UTC
EVENT END
31.01.2030 23:00 UTC
UNIT
Leventina
UNAVAILABILITY
147.00 MW